Guide 7 · 7 min read
Using your planning documents
Guide 7 of 7
Your estate was built under a planning permission. That permission, and the section 106 agreement that usually comes with it, often say exactly what should happen to the open space, the drainage and the landscaping, and who should look after them. Often it hasn't happened. The documents are public, and the council can enforce them. This guide shows what to look for and how to get the council to look.
In short
- A section 106 agreement often says the open space must be laid out by a deadline, maintained for a period, signed off by the council, then transferred to the council or to a management company.
- An approved SuDS management plan says who maintains the drainage and how often. Compare it with what you are billed for.
- Landscaping conditions often make the developer replace dead trees and plants for a set number of years.
- You usually can't enforce a section 106 yourself, but you can ask the council's planning enforcement team to investigate.
- Get the documents from the planning register, by an EIR request, or from HM Land Registry.
The section 106 open space lifecycle: where did your estate get stuck?
- 1
Permission granted, section 106 signed
The agreement sets out how the open space is built, looked after and handed over. It binds later owners of the land.
Stuck here? Get the agreement and any deeds of variation from the planning register.
- 2
Open space laid out by a trigger
Built to the approved plan by a set point, for example before a stated number of homes are occupied.
Stuck here? Was it finished on time, and as approved?
- 3
Developer maintains it for a set period
For a period the agreement sets, so planting can establish and defects come to light.
Stuck here? Who looked after it, and who paid: the developer, or residents through the estate charge?
- 4
Council inspects and signs it off
Often confirmed in writing. Some agreements treat it as approved if the council doesn't reply within a set time.
Stuck here? Ask the council: has it been signed off, and when?
- 5
Land transferred within a set time
The agreement usually allows one of two routes:
To the councilUsually with a one-off payment (a commuted sum) towards future upkeep. The council then maintains it.
To a management companyOne whose purpose is looking after the open space, sometimes with residents as members.
Stuck here? Download the title register for the open space. If the developer still owns it years after sign-off, ask the council why.
Looked after for goodBy the council, or by the company the agreement names, to the approved management plan. If you are still paying a developer or its agent for land that should have moved on, you have questions to ask.
The documents, and where to get them
- The decision notice: the planning permission and its conditions. Look for conditions on landscaping, open space, drainage and management plans.
- The section 106 agreement, and any later deeds of variation.
- Discharge of conditions applications: where the developer sent in the details a condition asked for. The approved SuDS management plan, landscape scheme and landscape management plan are often here.
- The approved plans, including the landscape masterplan.
Where to look
- The council's planning register. It must include each decision and a copy of any section 106 agreement made with it (guide 4). Search by the estate's name, the developer's name or the original site address.
- An Environmental Information Regulations (EIR) request, for anything not online. The ICO says planning information is often environmental information (guide 4). The council must reply within 20 working days. It may charge a reasonable amount for copies, but not for looking at a public register.
- HM Land Registry. Your title, or the title of the open space, may refer to the section 106 agreement. If the register says a copy is filed, order it with form OC2 (£11 per document). A section 106 obligation is also a local land charge.
- The council's infrastructure funding statement. Councils that receive section 106 money must publish one every year. It can show whether money for open space was received and spent.
Our templates include EIR requests for section 106 and SuDS documents.
What a section 106 says about open space
Every agreement is different, but open space clauses often follow the same pattern:
- Laying out. The developer must lay out the open space to an approved plan by a trigger, for example before a stated number of homes are occupied.
- A maintenance period. The developer must then maintain it for a set time.
- Sign-off. The council inspects it and confirms in writing that it is complete. Some agreements say it is treated as approved ("deemed" sign-off) if the council doesn't respond within a set time.
- Transfer. Within a set period after sign-off, the land must be transferred either to the council, usually with a one-off payment towards its upkeep (a commuted sum), or to a management company whose purpose is maintaining the open space.
A section 106 obligation binds whoever owns the land later, not just the developer who signed it (Town and Country Planning Act 1990, section 106(3)). The agreement may release an owner once it has sold its interest (section 106(4)).
Check where your estate got stuck
- Was the open space finished by the trigger?
- Has the council signed it off? When?
- Who owns it now? Download the title register (guide 4). If the developer still owns it years after sign-off, the transfer hasn't happened.
- If the agreement required a management company, was one set up, and is its purpose the open space?
- Does your deed, the section 106 and any management plan all describe the same arrangement? If they all promise a company that never existed, that is worth raising.
Drainage: the SuDS management plan
National planning policy says sustainable drainage systems should "have maintenance arrangements in place to ensure an acceptable standard of operation for the anticipated lifetime of the development" (National Planning Policy Framework, August 2026, policy F8). The government's non-statutory national standards for SuDS (June 2025) say the designer shall provide a management and maintenance plan, setting out who is responsible, the inspection and maintenance regime, and how often it happens.
If your permission has a drainage condition, it may require a plan like this to be approved, and then followed. This guide covers England. In Wales, new developments have needed their SuDS approved by a SuDS approving body since 2019 (guide 5).
How to check it's being done
- Find the approved plan in the discharge of conditions applications, or ask for it by EIR request.
- Note who it says is responsible, and how often each feature must be inspected and maintained.
- Compare it with your estate accounts. A drainage line budgeted every year but barely spent is a warning sign (guide 6).
- Ask the management company or agent for the inspection and maintenance records the plan requires.
- Look for yourself: blocked inlets, silted ponds, overgrown swales, standing water.
If a condition requires the drainage to be maintained in line with the approved plan, not doing so may be a breach of that condition. Failing to comply with a planning condition is a breach of planning control (section 171A), which the council can investigate.
Landscaping conditions
- A landscaping condition typically requires the planting to be carried out to an approved scheme.
- Some go further: any tree or plant that dies, is removed or is seriously damaged within a set number of years (for example five) must be replaced. The government's model wording lets the council choose the period, so check your decision notice.
- Some permissions also require a landscape management plan to be approved and then carried out.
If you are being billed through the estate charge for replacing planting that a condition says the developer must replace, ask why.
Can residents enforce a section 106?
Usually not. A section 106 obligation is enforceable by the local planning authority named in it (section 106(3)), and the agreement itself may say that nobody else can enforce it. But you can ask the council to act.
What the council can do
- For a section 106: seek an injunction (section 106(5)), or, after at least 21 days' notice, go onto the land, carry out the work itself and recover its costs (section 106(6)).
- For a planning condition: serve a breach of condition notice (section 187A) or an enforcement notice.
- Enforcement is discretionary. Government guidance says councils "have discretion to take enforcement action, when they regard it as expedient to do so", and should act proportionately.
- Don't wait. For most breaches of condition, enforcement action can't be taken more than ten years after the breach (section 171B(3)).
Questions to ask planning enforcement
Keep them factual. Ask the council to investigate, and to tell you:
- Has the open space been laid out and signed off under the section 106? On what date?
- Has the transfer the agreement requires taken place? To whom?
- Was any commuted sum paid?
- Was a management company set up as the agreement requires?
- Has the SuDS management plan been approved, and does the council consider it is being complied with?
- Are the landscaping and replacement planting conditions being complied with?
Attach the clauses, the title register for the open space, and your evidence, such as accounts and dated photos. Our templates include a planning enforcement complaint.
If the council won't look
Use the council's complaints process, and ask your councillors and MP for help. After that, the Local Government and Social Care Ombudsman can look at how the council handled it. It says "it is not our role to decide whether the council should take enforcement action", but it can look for fault in how the decision was made.
The commuted sum as a benchmark
If your section 106 set a commuted sum for the council to take on the open space, it shows what the council thought the upkeep would cost. That can be a useful comparison with what you now pay. Be careful with it:
- It usually covers only the open space, not roads, drainage, insurance or management.
- It is worked out over a set number of years, at the council's costs at the time.
- So it is not like-for-like with an annual estate charge. If you use it, say so.
A member's example (anonymised)
On one small estate, the owner's deed, the section 106 and the approved drainage plan all said a management company would be set up. None ever was. The section 106 required the open space to be transferred within a short period of council sign-off, either to the council with a commuted sum, or to a management company set up to maintain it. Years later, neither had happened: the developer still owned the land and charged residents through an agent. The owner sent the documents to the council's planning enforcement team, which opened an investigation.
Red flags
- The developer still owns the open space years after the homes were sold.
- A management company promised in the section 106 or your deed that was never set up.
- No one can show you the approved SuDS management plan, or the inspection records it requires.
- You are paying to replace planting the developer should have replaced.
- The council can't say whether the open space was ever signed off.
This guide explains how things usually work. It isn't legal advice, and your documents may say something different. For finding a solicitor, your options and ways out, see legal help.